Construction of a traction substation along with modernization of power supply and land development
Subcontracting in the scope (03.2019 – present):
- facade in the ETICS system with rustication (500 m2)
- roofing along with guttering
- plastering of internal walls
- construction of tracks for transformers and supporting structures for switchgear, rectifiers, and control cabinets
- installation of raised flooring
- mechanical ventilation with air intake
- external hardscaping with concrete pavers (600 m2)
- land development along with demolition of the existing traction substation